Slab

Concrete for a 10×10 ft slab, 4 in thick

A 10 ft × 10 ft slab poured 4 inches thick suits a patio, walkway or shed floor. Here is the volume and the bag count worked out from the standard slab formula, length × width × thickness.

Concrete needed

1.23cubic yards· 0.944· 33.33 ft³
Bags of premix needed for concrete for a 10×10 ft slab, 4 in thick, by bag size.
Bag sizeBags needed
40 lb112
60 lb75
80 lb56
25 kg81
30 kg68
Planning estimate, with no waste allowance included. Add 5-10% for spillage and over-excavation, and check the yield printed on your bag. Structural work must follow your local building code and an engineer's specification.
Bagged or ready-mix?
Either - check the short-load fee
1.23 yd³ clears the usual one-yard minimum but sits in the short-load band, where most suppliers add a surcharge for anything under about 3-4 yd³. That fee is what decides it: get it quoted, add it to the yard price, and compare against the bag count above at your own bag price.

At this size

What changes on a 10×10 ft slab, 4 in thick

What 4 in is for

At 4 in this is a foot-traffic slab - a patio, a path, a shed floor or a garden-office base. 4 in over a well-compacted sub-base carries people and furniture indefinitely, and will take an occasional light vehicle if the base is right, but it is not a driveway thickness. Fibre or a 6×6 mesh sheet is common at this depth; the sub-base does more for the slab than the reinforcement does.

Control joints for this size

At 10 × 10 ft this slab is small enough to pour as a single panel. Control joints go in at roughly 8-12 ft for a 4 in slab (24-36 times the thickness), and both dimensions here are inside that, so no intermediate joint is needed - just isolation material where the slab meets a wall, a step or a post.

Placing 100 ft²

The short side is 10 ft, so a straightedge resting on both forms strikes this off in one pass - a 12 ft screed board gives you the overhang you need at each end. Work back along the 10 ft direction and the whole 100 ft² is within reach of two people without stepping in it.

Mixing or ordering it

56 × 80 lb bags is 1.23 yd³ and roughly 28 mixer batches. This is the crossover point: bagging it is a full day with a mixer and at least two people, and the concrete has to keep arriving faster than the placed edge stiffens. Price 1.23 yd³ of ready-mix, short-load surcharge included, against 56 bags at your own bag price before you commit to a day of mixing.

How it is worked out

A slab is a simple rectangular prism: multiply length × width × thickness. Enter the thickness in inches (it is usually the smallest dimension) and the plan size in feet. Four inches suits patios and walkways; drives and garage floors are usually five to six.

That volume - 33.33 ft³ - is divided by 27 to give 1.23 cubic yards, and by each bag's yield to give the bag count. An 80 lb bag of premix yields about 0.60 cubic feet, so this job takes 56 of them; bag counts always round up, because you cannot buy part of a bag.

Ordering ready-mix instead? Suppliers sell by the cubic yard (or cubic metre) and usually have a minimum load and a short-load surcharge - worth a call before you choose between bags and a truck.

Formwork

What is being measured

lengththicknesswidth runs into the pageSLAB · L × W × T