Slab

Concrete for a 10×20 ft slab, 5 in thick

A 10 ft × 20 ft slab poured 5 inches thick suits a residential driveway or workshop floor. Here is the volume and the bag count worked out from the standard slab formula, length × width × thickness.

Concrete needed

3.09cubic yards· 2.36· 83.33 ft³
Bags of premix needed for concrete for a 10×20 ft slab, 5 in thick, by bag size.
Bag sizeBags needed
40 lb278
60 lb186
80 lb139
25 kg202
30 kg168
Planning estimate, with no waste allowance included. Add 5-10% for spillage and over-excavation, and check the yield printed on your bag. Structural work must follow your local building code and an engineer's specification.
Bagged or ready-mix?
Ready-mix
3.09 yd³ is comfortably past the short-load band and inside a single truck. Ready-mix will almost certainly be cheaper than bags here, and it arrives as one continuous pour instead of however many batches you can mix in a row. The bag count above is for costing the comparison, not for planning the day.

At this size

What changes on a 10×20 ft slab, 5 in thick

What 5 in is for

5 in is the in-between thickness people land on when a slab has to take a car but is not a working yard - a domestic driveway, a workshop floor, a caravan or boat pad. It is a real step up from 4 in for wheel loads, and it is where reinforcement starts being worth the money rather than optional.

Control joints for this size

A 5 in slab wants control joints every 10-15 ft - 24 to 36 times its thickness. At 10 × 20 ft that is about 1 joint: 1 across the 20 ft width (2 panels of about 10 ft). That keeps the panels close to square, which is what stops a joint being ignored and a crack appearing somewhere else. Cut or tool them about 1.25 in deep - a quarter of the slab - and do it within the first day, before the slab decides where to crack on its own.

Placing 200 ft²

The short side is 10 ft, so a straightedge resting on both forms strikes this off in one pass - a 12 ft screed board gives you the overhang you need at each end. Work back along the 20 ft direction and the whole 200 ft² is within reach of two people without stepping in it.

Mixing or ordering it

139 × 80 lb bags is 3.09 yd³ - about 70 mixer batches. At this size the bag count is a costing reference rather than a plan: mixing 139 bags on site cannot keep ahead of the setting edge, so the pour ends up full of cold joints. Ordered by the yard it is part of a single load. Have the crew, the access and the discharge points sorted before anything arrives.

How it is worked out

A slab is a simple rectangular prism: multiply length × width × thickness. Enter the thickness in inches (it is usually the smallest dimension) and the plan size in feet. Four inches suits patios and walkways; drives and garage floors are usually five to six.

That volume - 83.33 ft³ - is divided by 27 to give 3.09 cubic yards, and by each bag's yield to give the bag count. An 80 lb bag of premix yields about 0.60 cubic feet, so this job takes 139 of them; bag counts always round up, because you cannot buy part of a bag.

Ordering ready-mix instead? Suppliers sell by the cubic yard (or cubic metre) and usually have a minimum load and a short-load surcharge - worth a call before you choose between bags and a truck.

Formwork

What is being measured

lengththicknesswidth runs into the pageSLAB · L × W × T

Nearby

More slab examples