Post holes

Concrete for 12 × 12 in post holes, 48 in deep

12 deck posts in 12 in diameter holes, 48 in deep, set around a nominal 4×4 post (3.5 in actual). The concrete fills the ring around each post; here is the total volume and bag count.

Concrete needed

1.25cubic yards· 0.952· 33.62 ft³
Bags of premix needed for concrete for 12 × 12 in post holes, 48 in deep, by bag size.
Bag sizeBags needed
40 lb113
60 lb75
80 lb57
25 kg82
30 kg68
Planning estimate, with no waste allowance included. Add 5-10% for spillage and over-excavation, and check the yield printed on your bag. Structural work must follow your local building code and an engineer's specification.
Bagged or ready-mix?
Either - check the short-load fee
1.25 yd³ clears the usual one-yard minimum but sits in the short-load band, where most suppliers add a surcharge for anything under about 3-4 yd³. That fee is what decides it: get it quoted, add it to the yard price, and compare against the bag count above at your own bag price.

At this size

What changes on 12 × 12 in post holes, 48 in deep

Mixing or ordering it

57 × 80 lb bags is 1.25 yd³ and roughly 29 mixer batches. This is the crossover point: bagging it is a full day with a mixer and at least two people, and the concrete has to keep arriving faster than the placed edge stiffens. Price 1.25 yd³ of ready-mix, short-load surcharge included, against 57 bags at your own bag price before you commit to a day of mixing.

How it is worked out

Each post hole is a cylinder - π·(diameter/2)² × depth - and the concrete only fills the space around a set post, so the post's cross-section is subtracted. Enter a post size of 0 to fill the whole hole as a mass footing.

That volume - 33.62 ft³ - is divided by 27 to give 1.25 cubic yards, and by each bag's yield to give the bag count. An 80 lb bag of premix yields about 0.60 cubic feet, so this job takes 57 of them; bag counts always round up, because you cannot buy part of a bag.

Ordering ready-mix instead? Suppliers sell by the cubic yard (or cubic metre) and usually have a minimum load and a short-load surcharge - worth a call before you choose between bags and a truck.

Formwork

What is being measured

gradeposthole Ødepthfill around postPOST HOLE FOOTING