Column

Concrete for a 12 in sonotube, 4 ft tall

A single 12 in diameter round column (sonotube) 4 ft tall. The volume is the circle area π·(diameter/2)² times the height; multiply the bag counts by the number of piers you are pouring.

Concrete needed

0.12cubic yards· 0.089· 3.14 ft³
Bags of premix needed for concrete for a 12 in sonotube, 4 ft tall, by bag size.
Bag sizeBags needed
40 lb11
60 lb7
80 lb6
25 kg8
30 kg7
Planning estimate, with no waste allowance included. Add 5-10% for spillage and over-excavation, and check the yield printed on your bag. Structural work must follow your local building code and an engineer's specification.
Bagged or ready-mix?
Bags
0.12 yd³ is under a ready-mix supplier's usual one-yard minimum, so bags are the answer whatever the price per yard says. Buy a couple more than the count above and return what you do not open.

At this size

What changes on a 12 in sonotube, 4 ft tall

Mixing or ordering it

6 × 80 lb bags is 0.12 yd³ - a wheelbarrow-and-shovel job. Mix two bags at a time, keep the water tight to the bag's own figure, and place it in one go so there is no cold joint. No mixer, no delivery, no minimum load.

How it is worked out

A round column or sonotube form holds a cylinder of concrete: area π·(diameter/2)² times its height, multiplied by how many you are pouring. Enter the tube's inside diameter - that is the finished column diameter.

That volume - 3.14 ft³ - is divided by 27 to give 0.12 cubic yards, and by each bag's yield to give the bag count. An 80 lb bag of premix yields about 0.60 cubic feet, so this job takes 6 of them; bag counts always round up, because you cannot buy part of a bag.

Ordering ready-mix instead? Suppliers sell by the cubic yard (or cubic metre) and usually have a minimum load and a short-load surcharge - worth a call before you choose between bags and a truck.

Formwork

What is being measured

diameterheightV = π·r²·hROUND COLUMN / SONOTUBE