Concrete for a 12×14 ft slab, 6 in thick

A 12 ft × 14 ft slab poured 6 inches thick suits a driveway, garage floor or heavy-load pad. Here is the volume and the bag count worked out from the standard slab formula, length × width × thickness.

Concrete needed

3.11cubic yards· 2.379· 84 ft³
Bags of premix needed for concrete for a 12×14 ft slab, 6 in thick, by bag size.
Bag sizeBags needed
40 lb280
60 lb187
80 lb140
25 kg204
30 kg170
Planning estimate, with no waste allowance included. Add 5-10% for spillage and over-excavation, and check the yield printed on your bag. Structural work must follow your local building code and an engineer's specification.
Bagged or ready-mix?
Ready-mix
3.11 yd³ is comfortably past the short-load band and inside a single truck. Ready-mix will almost certainly be cheaper than bags here, and it arrives as one continuous pour instead of however many batches you can mix in a row. The bag count above is for costing the comparison, not for planning the day.

At this size

What changes on a 12×14 ft slab, 6 in thick

What 6 in is for

6 in is a load thickness: repeated vehicle traffic, a garage or shop floor, a machine or skip pad, anything with a point load. At this depth reinforcement is assumed rather than optional, and the sub-base needs to be as good as the slab - a 6 in slab on soft ground still cracks.

Control joints for this size

At 12 × 14 ft this slab is small enough to pour as a single panel. Control joints go in at roughly 12-18 ft for a 6 in slab (24-36 times the thickness), and both dimensions here are inside that, so no intermediate joint is needed - just isolation material where the slab meets a wall, a step or a post.

Placing 168 ft²

The short side is 12 ft, so a straightedge resting on both forms strikes this off in one pass - a 14 ft screed board gives you the overhang you need at each end. Work back along the 14 ft direction and the whole 168 ft² is within reach of two people without stepping in it.

Mixing or ordering it

140 × 80 lb bags is 3.11 yd³ - about 70 mixer batches. At this size the bag count is a costing reference rather than a plan: mixing 140 bags on site cannot keep ahead of the setting edge, so the pour ends up full of cold joints. Ordered by the yard it is part of a single load. Have the crew, the access and the discharge points sorted before anything arrives.

How it is worked out

A slab is a simple rectangular prism: multiply length × width × thickness. Enter the thickness in inches (it is usually the smallest dimension) and the plan size in feet. Four inches suits patios and walkways; drives and garage floors are usually five to six.

That volume - 84 ft³ - is divided by 27 to give 3.11 cubic yards, and by each bag's yield to give the bag count. An 80 lb bag of premix yields about 0.60 cubic feet, so this job takes 140 of them; bag counts always round up, because you cannot buy part of a bag.

Ordering ready-mix instead? Suppliers sell by the cubic yard (or cubic metre) and usually have a minimum load and a short-load surcharge - worth a call before you choose between bags and a truck.

Formwork

What is being measured

lengththicknesswidth runs into the pageSLAB · L × W × T