Slab

Concrete for a 12×16 ft slab, 4 in thick

A 12 ft × 16 ft slab poured 4 inches thick suits a patio, walkway or shed floor. Here is the volume and the bag count worked out from the standard slab formula, length × width × thickness.

Concrete needed

2.37cubic yards· 1.812· 64 ft³
Bags of premix needed for concrete for a 12×16 ft slab, 4 in thick, by bag size.
Bag sizeBags needed
40 lb214
60 lb143
80 lb107
25 kg155
30 kg130
Planning estimate, with no waste allowance included. Add 5-10% for spillage and over-excavation, and check the yield printed on your bag. Structural work must follow your local building code and an engineer's specification.
Bagged or ready-mix?
Either - check the short-load fee
2.37 yd³ clears the usual one-yard minimum but sits in the short-load band, where most suppliers add a surcharge for anything under about 3-4 yd³. That fee is what decides it: get it quoted, add it to the yard price, and compare against the bag count above at your own bag price.

At this size

What changes on a 12×16 ft slab, 4 in thick

What 4 in is for

At 4 in this is a foot-traffic slab - a patio, a path, a shed floor or a garden-office base. 4 in over a well-compacted sub-base carries people and furniture indefinitely, and will take an occasional light vehicle if the base is right, but it is not a driveway thickness. Fibre or a 6×6 mesh sheet is common at this depth; the sub-base does more for the slab than the reinforcement does.

Control joints for this size

A 4 in slab wants control joints every 8-12 ft - 24 to 36 times its thickness. At 12 × 16 ft that is about 2 joints: 1 across the 12 ft length (2 panels of about 6 ft) and 1 across the 16 ft width (2 panels of about 8 ft). That keeps the panels close to square, which is what stops a joint being ignored and a crack appearing somewhere else. Cut or tool them about 1 in deep - a quarter of the slab - and do it within the first day, before the slab decides where to crack on its own.

Placing 192 ft²

The short side is 12 ft, so a straightedge resting on both forms strikes this off in one pass - a 14 ft screed board gives you the overhang you need at each end. Work back along the 16 ft direction and the whole 192 ft² is within reach of two people without stepping in it.

Mixing or ordering it

107 × 80 lb bags is 2.37 yd³ - about 54 mixer batches. At this size the bag count is a costing reference rather than a plan: mixing 107 bags on site cannot keep ahead of the setting edge, so the pour ends up full of cold joints. Ordered by the yard it is part of a single load. Have the crew, the access and the discharge points sorted before anything arrives.

How it is worked out

A slab is a simple rectangular prism: multiply length × width × thickness. Enter the thickness in inches (it is usually the smallest dimension) and the plan size in feet. Four inches suits patios and walkways; drives and garage floors are usually five to six.

That volume - 64 ft³ - is divided by 27 to give 2.37 cubic yards, and by each bag's yield to give the bag count. An 80 lb bag of premix yields about 0.60 cubic feet, so this job takes 107 of them; bag counts always round up, because you cannot buy part of a bag.

Ordering ready-mix instead? Suppliers sell by the cubic yard (or cubic metre) and usually have a minimum load and a short-load surcharge - worth a call before you choose between bags and a truck.

Formwork

What is being measured

lengththicknesswidth runs into the pageSLAB · L × W × T

Nearby