Slab

Concrete for a 16×24 ft slab, 4 in thick

A 16 ft × 24 ft slab poured 4 inches thick suits a patio, walkway or shed floor. Here is the volume and the bag count worked out from the standard slab formula, length × width × thickness.

Concrete needed

4.74cubic yards· 3.625· 128 ft³
Bags of premix needed for concrete for a 16×24 ft slab, 4 in thick, by bag size.
Bag sizeBags needed
40 lb427
60 lb285
80 lb214
25 kg310
30 kg259
Planning estimate, with no waste allowance included. Add 5-10% for spillage and over-excavation, and check the yield printed on your bag. Structural work must follow your local building code and an engineer's specification.
Bagged or ready-mix?
Ready-mix
4.74 yd³ is comfortably past the short-load band and inside a single truck. Ready-mix will almost certainly be cheaper than bags here, and it arrives as one continuous pour instead of however many batches you can mix in a row. The bag count above is for costing the comparison, not for planning the day.

At this size

What changes on a 16×24 ft slab, 4 in thick

What 4 in is for

At 4 in this is a foot-traffic slab - a patio, a path, a shed floor or a garden-office base. 4 in over a well-compacted sub-base carries people and furniture indefinitely, and will take an occasional light vehicle if the base is right, but it is not a driveway thickness. Fibre or a 6×6 mesh sheet is common at this depth; the sub-base does more for the slab than the reinforcement does.

Control joints for this size

A 4 in slab wants control joints every 8-12 ft - 24 to 36 times its thickness. At 16 × 24 ft that is about 3 joints: 1 across the 16 ft length (2 panels of about 8 ft) and 2 across the 24 ft width (3 panels of about 8 ft). That keeps the panels close to square, which is what stops a joint being ignored and a crack appearing somewhere else. Cut or tool them about 1 in deep - a quarter of the slab - and do it within the first day, before the slab decides where to crack on its own.

Placing 384 ft²

At 16 ft across, this is past the width a screed board spans. Set 1 intermediate wet screed or screed rail down the 24 ft direction, dividing it into strips of about 8 ft, and strike off strip by strip. 384 ft² also has to be placed and finished before the first of it sets, so this is a crew job, not a weekend-alone job.

Mixing or ordering it

214 × 80 lb bags is 4.74 yd³ - about 107 mixer batches. At this size the bag count is a costing reference rather than a plan: mixing 214 bags on site cannot keep ahead of the setting edge, so the pour ends up full of cold joints. Ordered by the yard it is part of a single load. Have the crew, the access and the discharge points sorted before anything arrives.

How it is worked out

A slab is a simple rectangular prism: multiply length × width × thickness. Enter the thickness in inches (it is usually the smallest dimension) and the plan size in feet. Four inches suits patios and walkways; drives and garage floors are usually five to six.

That volume - 128 ft³ - is divided by 27 to give 4.74 cubic yards, and by each bag's yield to give the bag count. An 80 lb bag of premix yields about 0.60 cubic feet, so this job takes 214 of them; bag counts always round up, because you cannot buy part of a bag.

Ordering ready-mix instead? Suppliers sell by the cubic yard (or cubic metre) and usually have a minimum load and a short-load surcharge - worth a call before you choose between bags and a truck.

Formwork

What is being measured

lengththicknesswidth runs into the pageSLAB · L × W × T

Nearby

More slab examples