Slab

Concrete for a 20×20 ft slab, 6 in thick

A 20 ft × 20 ft slab poured 6 inches thick suits a driveway, garage floor or heavy-load pad. Here is the volume and the bag count worked out from the standard slab formula, length × width × thickness.

Concrete needed

7.41cubic yards· 5.663· 200 ft³
Bags of premix needed for concrete for a 20×20 ft slab, 6 in thick, by bag size.
Bag sizeBags needed
40 lb667
60 lb445
80 lb334
25 kg484
30 kg404
Planning estimate, with no waste allowance included. Add 5-10% for spillage and over-excavation, and check the yield printed on your bag. Structural work must follow your local building code and an engineer's specification.
Bagged or ready-mix?
Ready-mix
7.41 yd³ is comfortably past the short-load band and inside a single truck. Ready-mix will almost certainly be cheaper than bags here, and it arrives as one continuous pour instead of however many batches you can mix in a row. The bag count above is for costing the comparison, not for planning the day.

At this size

What changes on a 20×20 ft slab, 6 in thick

What 6 in is for

6 in is a load thickness: repeated vehicle traffic, a garage or shop floor, a machine or skip pad, anything with a point load. At this depth reinforcement is assumed rather than optional, and the sub-base needs to be as good as the slab - a 6 in slab on soft ground still cracks.

Control joints for this size

A 6 in slab wants control joints every 12-18 ft - 24 to 36 times its thickness. At 20 × 20 ft that is about 2 joints: 1 across the 20 ft length (2 panels of about 10 ft) and 1 across the 20 ft width (2 panels of about 10 ft). That keeps the panels close to square, which is what stops a joint being ignored and a crack appearing somewhere else. Cut or tool them about 1.5 in deep - a quarter of the slab - and do it within the first day, before the slab decides where to crack on its own.

Placing 400 ft²

At 20 ft across, this is past the width a screed board spans. Set 1 intermediate wet screed or screed rail down the 20 ft direction, dividing it into strips of about 10 ft, and strike off strip by strip. 400 ft² also has to be placed and finished before the first of it sets, so this is a crew job, not a weekend-alone job.

Mixing or ordering it

334 × 80 lb bags is 7.41 yd³ - about 167 mixer batches. At this size the bag count is a costing reference rather than a plan: mixing 334 bags on site cannot keep ahead of the setting edge, so the pour ends up full of cold joints. Ordered by the yard it is part of a single load. Have the crew, the access and the discharge points sorted before anything arrives.

How it is worked out

A slab is a simple rectangular prism: multiply length × width × thickness. Enter the thickness in inches (it is usually the smallest dimension) and the plan size in feet. Four inches suits patios and walkways; drives and garage floors are usually five to six.

That volume - 200 ft³ - is divided by 27 to give 7.41 cubic yards, and by each bag's yield to give the bag count. An 80 lb bag of premix yields about 0.60 cubic feet, so this job takes 334 of them; bag counts always round up, because you cannot buy part of a bag.

Ordering ready-mix instead? Suppliers sell by the cubic yard (or cubic metre) and usually have a minimum load and a short-load surcharge - worth a call before you choose between bags and a truck.

Formwork

What is being measured

lengththicknesswidth runs into the pageSLAB · L × W × T

Nearby

More slab examples