What 4 in is for
At 4 in this is a foot-traffic slab - a patio, a path, a shed floor or a garden-office base. 4 in over a well-compacted sub-base carries people and furniture indefinitely, and will take an occasional light vehicle if the base is right, but it is not a driveway thickness. Fibre or a 6×6 mesh sheet is common at this depth; the sub-base does more for the slab than the reinforcement does.
Control joints for this size
A 4 in slab wants control joints every 8-12 ft - 24 to 36 times its thickness. At 40 × 60 ft that is about 8 joints: 3 across the 40 ft length (4 panels of about 10 ft) and 5 across the 60 ft width (6 panels of about 10 ft). That keeps the panels close to square, which is what stops a joint being ignored and a crack appearing somewhere else. Cut or tool them about 1 in deep - a quarter of the slab - and do it within the first day, before the slab decides where to crack on its own.
Placing 2400 ft²
At 40 ft across, this is past the width a screed board spans. Set 3 intermediate wet screeds or screed rails down the 60 ft direction, dividing it into strips of about 10 ft, and strike off strip by strip. 2400 ft² also has to be placed and finished before the first of it sets, so this is a crew job, not a weekend-alone job.
Mixing or ordering it
1334 × 80 lb bags is 29.63 yd³ - about 667 mixer batches. At this size the bag count is a costing reference rather than a plan: mixing 1334 bags on site cannot keep ahead of the setting edge, so the pour ends up full of cold joints. Ordered by the yard it is about 4 loads at a typical 9 yd³ truck, booked back to back. Have the crew, the access and the discharge points sorted before anything arrives.