Slab

Concrete for a 8×8 ft slab, 5 in thick

A 8 ft × 8 ft slab poured 5 inches thick suits a residential driveway or workshop floor. Here is the volume and the bag count worked out from the standard slab formula, length × width × thickness.

Concrete needed

0.99cubic yards· 0.755· 26.67 ft³
Bags of premix needed for concrete for a 8×8 ft slab, 5 in thick, by bag size.
Bag sizeBags needed
40 lb89
60 lb60
80 lb45
25 kg65
30 kg54
Planning estimate, with no waste allowance included. Add 5-10% for spillage and over-excavation, and check the yield printed on your bag. Structural work must follow your local building code and an engineer's specification.
Bagged or ready-mix?
Bags
0.99 yd³ is under a ready-mix supplier's usual one-yard minimum, so bags are the answer whatever the price per yard says. Buy a couple more than the count above and return what you do not open.

At this size

What changes on a 8×8 ft slab, 5 in thick

What 5 in is for

5 in is the in-between thickness people land on when a slab has to take a car but is not a working yard - a domestic driveway, a workshop floor, a caravan or boat pad. It is a real step up from 4 in for wheel loads, and it is where reinforcement starts being worth the money rather than optional.

Control joints for this size

At 8 × 8 ft this slab is small enough to pour as a single panel. Control joints go in at roughly 10-15 ft for a 5 in slab (24-36 times the thickness), and both dimensions here are inside that, so no intermediate joint is needed - just isolation material where the slab meets a wall, a step or a post.

Placing 64 ft²

The short side is 8 ft, so a straightedge resting on both forms strikes this off in one pass - a 10 ft screed board gives you the overhang you need at each end. Work back along the 8 ft direction and the whole 64 ft² is within reach of two people without stepping in it.

Mixing or ordering it

45 × 80 lb bags is 0.99 yd³ and roughly 23 mixer batches. This is the crossover point: bagging it is a full day with a mixer and at least two people, and the concrete has to keep arriving faster than the placed edge stiffens. 0.99 yd³ is still under the usual one-yard delivery minimum, so plan the day around keeping the mixer fed rather than around a truck.

How it is worked out

A slab is a simple rectangular prism: multiply length × width × thickness. Enter the thickness in inches (it is usually the smallest dimension) and the plan size in feet. Four inches suits patios and walkways; drives and garage floors are usually five to six.

That volume - 26.67 ft³ - is divided by 27 to give 0.99 cubic yards, and by each bag's yield to give the bag count. An 80 lb bag of premix yields about 0.60 cubic feet, so this job takes 45 of them; bag counts always round up, because you cannot buy part of a bag.

Ordering ready-mix instead? Suppliers sell by the cubic yard (or cubic metre) and usually have a minimum load and a short-load surcharge - worth a call before you choose between bags and a truck.