Concrete for a 100 ft curb

A 100 ft run of plain curb, 6 in wide and 18 in tall. The volume is the curb cross-section times the run. That is 75 cubic feet, or 2.78 cubic yards: 125 bags of 80 lb premix or 167 bags of 60 lb, before any waste.

Concrete needed

2.78cubic yards· 2.124 m³· 75 ft³
Bags of premix needed for concrete for a 100 ft curb, by bag size.
Bag sizeBags needed
40 lb250
60 lb167
80 lb125
25 kg182
30 kg152
Planning estimate, with no waste allowance included. Add 5-10% for spillage and over-excavation, and check the yield printed on your bag. Structural work must follow your local building code and an engineer's specification.
Bagged or ready-mix?
Either - check the short-load fee
2.78 yd³ clears the usual one-yard minimum but sits in the short-load band, where most suppliers add a surcharge for anything under about 3-4 yd³. That fee is what decides it: get it quoted, add it to the yard price, and compare against the bag count above at your own bag price.

Same job, other sizes

Plain curb

Volume for each size. The order columns add 10%, the top of the 5-10% waste allowance, and round bags up.
Sizeft³yd³yd³ to order (+10%)80 lb bags (+10%)60 lb bags (+10%)
20 ft run150.560.612837
50 ft run37.51.391.536992
100 ft run (this page)752.783.06138184

At this size

What changes on a 100 ft curb

Mixing or ordering it

125 × 80 lb bags is 2.78 yd³ - about 63 mixer batches. At this size the bag count is a costing reference rather than a plan: mixing 125 bags on site cannot keep ahead of the setting edge, so the pour ends up full of cold joints. Ordered by the yard it is part of a single load. Have the crew, the access and the discharge points sorted before anything arrives.

How it is worked out

A curb is a long prism: its cross-section (width × height) times the run. For curb-and-gutter, the flat gutter pan (width × thickness) is added to the cross-section before multiplying by the length.

That volume - 75 ft³ - is divided by 27 to give 2.78 cubic yards, and by each bag's yield to give the bag count. An 80 lb bag of premix yields about 0.60 cubic feet, so this job takes 125 of them; bag counts always round up, because you cannot buy part of a bag.

Ordering ready-mix instead? Suppliers sell by the cubic yard (or cubic metre) and usually have a minimum load and a short-load surcharge - worth a call before you choose between bags and a truck.