Per unit
The stepped cross-section is 10 blocks of 7 × 11 in (1 + 2 + 3 + 4), 5.35 ft² in all, so each extra foot of width adds 5.35 ft³.
Change the dimensions in the steps calculator. Why every count rounds up: how many bags of concrete you need.
Steps
A solid poured staircase of 4 steps, 4 ft wide, with 7 in rises and 11 in treads. The volume is the stacked step cross-section times the width. That is 21.39 cubic feet, or 0.79 cubic yards: 36 bags of 80 lb premix or 48 bags of 60 lb, before any waste.
Concrete needed
| Bag size | Bags needed |
|---|---|
| 40 lb | 72 |
| 60 lb | 48 |
| 80 lb | 36 |
| 25 kg | 52 |
| 30 kg | 44 |
Same job, other sizes
| Size | ft³ | yd³ | yd³ to order (+10%) | 80 lb bags (+10%) | 60 lb bags (+10%) |
|---|---|---|---|---|---|
| 2 steps | 6.42 | 0.24 | 0.26 | 12 | 16 |
| 3 steps | 12.83 | 0.48 | 0.52 | 24 | 32 |
| 4 steps (this page) | 21.39 | 0.79 | 0.87 | 40 | 53 |
| 5 steps | 32.08 | 1.19 | 1.31 | 59 | 79 |
| 6 steps | 44.92 | 1.66 | 1.83 | 83 | 110 |
The stepped cross-section is 10 blocks of 7 × 11 in (1 + 2 + 3 + 4), 5.35 ft² in all, so each extra foot of width adds 5.35 ft³.
Change the dimensions in the steps calculator. Why every count rounds up: how many bags of concrete you need.
At this size
36 × 80 lb bags is 0.79 yd³, which is about 18 batches in a 6 ft³ site mixer at two bags a batch. That is a comfortable half-day for two people - one mixing, one placing - and at 0.79 yd³ you are under the one-yard minimum most ready-mix suppliers will deliver, so bagging it is the route regardless of price.
| Steps | 4 |
|---|---|
| Rise | 7 in |
| Run | 11 in |
| Width | 4 ft |
A solid poured staircase is a stack of rectangular blocks: the cross-section area is rise × run × n(n+1)/2 for n steps, and the volume is that area times the stair width. Seven-inch rises with eleven-inch runs are a comfortable, code-typical stair.
That volume - 21.39 ft³ - is divided by 27 to give 0.79 cubic yards, and by each bag's yield to give the bag count. An 80 lb bag of premix yields about 0.60 cubic feet, so this job takes 36 of them; bag counts always round up, because you cannot buy part of a bag.
Ordering ready-mix instead? Suppliers sell by the cubic yard (or cubic metre) and usually have a minimum load and a short-load surcharge - worth a call before you choose between bags and a truck.
Formwork