Footing

Concrete for a 10 ft footing, 24×12 in

A 10 ft run of 24 in × 12 in strip footing. The volume is the trench cross-section times the run. That is 20 cubic feet, or 0.74 cubic yards: 34 bags of 80 lb premix or 45 bags of 60 lb, before any waste.

Concrete needed

0.74cubic yards· 0.566 m³· 20 ft³
Bags of premix needed for concrete for a 10 ft footing, 24×12 in, by bag size.
Bag sizeBags needed
40 lb67
60 lb45
80 lb34
25 kg49
30 kg41
Planning estimate, with no waste allowance included. Add 5-10% for spillage and over-excavation, and check the yield printed on your bag. Structural work must follow your local building code and an engineer's specification.
Bagged or ready-mix?
Bags
0.74 yd³ is under a ready-mix supplier's usual one-yard minimum, so bags are the answer whatever the price per yard says. Buy a couple more than the count above and return what you do not open.

Same job, other sizes

24 × 12 in footing

Volume for each size. The order columns add 10%, the top of the 5-10% waste allowance, and round bags up.
Sizeft³yd³yd³ to order (+10%)80 lb bags (+10%)60 lb bags (+10%)
10 ft run (this page)200.740.813749
15 ft run301.111.225574
20 ft run401.481.637498
24 ft run481.781.9688118
30 ft run602.222.44110147
40 ft run802.963.26147196
50 ft run1003.74.07184245
60 ft run1204.444.89220294
80 ft run1605.936.52294392
100 ft run2007.418.15367489

At this size

What changes on a 10 ft footing, 24×12 in

Mixing or ordering it

34 × 80 lb bags is 0.74 yd³, which is about 17 batches in a 6 ft³ site mixer at two bags a batch. That is a comfortable half-day for two people - one mixing, one placing - and at 0.74 yd³ you are under the one-yard minimum most ready-mix suppliers will deliver, so bagging it is the route regardless of price.

How it is worked out

A strip footing is a long rectangular prism under a wall; a spread footing is a pad under a column. Either way the volume is length × width × depth. Enter the total run of the footing as the length, and the trench cross-section as width × depth.

That volume - 20 ft³ - is divided by 27 to give 0.74 cubic yards, and by each bag's yield to give the bag count. An 80 lb bag of premix yields about 0.60 cubic feet, so this job takes 34 of them; bag counts always round up, because you cannot buy part of a bag.

Ordering ready-mix instead? Suppliers sell by the cubic yard (or cubic metre) and usually have a minimum load and a short-load surcharge - worth a call before you choose between bags and a truck.

Formwork

What is being measured

wall aboverun / lengthdepthwidth acrossSTRIP FOOTING