Footing

Concrete for a 40 ft footing, 24×12 in

A 40 ft run of 24 in × 12 in strip footing. The volume is simply the trench cross-section times the run; here it is worked out with the bag counts.

Concrete needed

2.96cubic yards· 2.265· 80 ft³
Bags of premix needed for concrete for a 40 ft footing, 24×12 in, by bag size.
Bag sizeBags needed
40 lb267
60 lb178
80 lb134
25 kg194
30 kg162
Planning estimate, with no waste allowance included. Add 5-10% for spillage and over-excavation, and check the yield printed on your bag. Structural work must follow your local building code and an engineer's specification.
Bagged or ready-mix?
Either - check the short-load fee
2.96 yd³ clears the usual one-yard minimum but sits in the short-load band, where most suppliers add a surcharge for anything under about 3-4 yd³. That fee is what decides it: get it quoted, add it to the yard price, and compare against the bag count above at your own bag price.

At this size

What changes on a 40 ft footing, 24×12 in

Mixing or ordering it

134 × 80 lb bags is 2.96 yd³ - about 67 mixer batches. At this size the bag count is a costing reference rather than a plan: mixing 134 bags on site cannot keep ahead of the setting edge, so the pour ends up full of cold joints. Ordered by the yard it is part of a single load. Have the crew, the access and the discharge points sorted before anything arrives.

How it is worked out

A strip footing is a long rectangular prism under a wall; a spread footing is a pad under a column. Either way the volume is length × width × depth. Enter the total run of the footing as the length, and the trench cross-section as width × depth.

That volume - 80 ft³ - is divided by 27 to give 2.96 cubic yards, and by each bag's yield to give the bag count. An 80 lb bag of premix yields about 0.60 cubic feet, so this job takes 134 of them; bag counts always round up, because you cannot buy part of a bag.

Ordering ready-mix instead? Suppliers sell by the cubic yard (or cubic metre) and usually have a minimum load and a short-load surcharge - worth a call before you choose between bags and a truck.

Formwork

What is being measured

wall aboverun / lengthdepthwidth acrossSTRIP FOOTING