Footing

Concrete for a 100 ft footing, 16×8 in

A 100 ft run of 16 in × 8 in strip footing. The volume is simply the trench cross-section times the run; here it is worked out with the bag counts.

Concrete needed

3.29cubic yards· 2.517· 88.89 ft³
Bags of premix needed for concrete for a 100 ft footing, 16×8 in, by bag size.
Bag sizeBags needed
40 lb297
60 lb198
80 lb149
25 kg216
30 kg180
Planning estimate, with no waste allowance included. Add 5-10% for spillage and over-excavation, and check the yield printed on your bag. Structural work must follow your local building code and an engineer's specification.
Bagged or ready-mix?
Ready-mix
3.29 yd³ is comfortably past the short-load band and inside a single truck. Ready-mix will almost certainly be cheaper than bags here, and it arrives as one continuous pour instead of however many batches you can mix in a row. The bag count above is for costing the comparison, not for planning the day.

At this size

What changes on a 100 ft footing, 16×8 in

Mixing or ordering it

149 × 80 lb bags is 3.29 yd³ - about 75 mixer batches. At this size the bag count is a costing reference rather than a plan: mixing 149 bags on site cannot keep ahead of the setting edge, so the pour ends up full of cold joints. Ordered by the yard it is part of a single load. Have the crew, the access and the discharge points sorted before anything arrives.

How it is worked out

A strip footing is a long rectangular prism under a wall; a spread footing is a pad under a column. Either way the volume is length × width × depth. Enter the total run of the footing as the length, and the trench cross-section as width × depth.

That volume - 88.89 ft³ - is divided by 27 to give 3.29 cubic yards, and by each bag's yield to give the bag count. An 80 lb bag of premix yields about 0.60 cubic feet, so this job takes 149 of them; bag counts always round up, because you cannot buy part of a bag.

Ordering ready-mix instead? Suppliers sell by the cubic yard (or cubic metre) and usually have a minimum load and a short-load surcharge - worth a call before you choose between bags and a truck.