Footing

Concrete for a 50 ft footing, 24×12 in

A 50 ft run of 24 in × 12 in strip footing. The volume is the trench cross-section times the run. That is 100 cubic feet, or 3.7 cubic yards: 167 bags of 80 lb premix or 223 bags of 60 lb, before any waste.

Concrete needed

3.7cubic yards· 2.832 m³· 100 ft³
Bags of premix needed for concrete for a 50 ft footing, 24×12 in, by bag size.
Bag sizeBags needed
40 lb334
60 lb223
80 lb167
25 kg242
30 kg202
Planning estimate, with no waste allowance included. Add 5-10% for spillage and over-excavation, and check the yield printed on your bag. Structural work must follow your local building code and an engineer's specification.
Bagged or ready-mix?
Ready-mix
3.7 yd³ is comfortably past the short-load band and inside a single truck. Ready-mix will almost certainly be cheaper than bags here, and it arrives as one continuous pour instead of however many batches you can mix in a row. The bag count above is for costing the comparison, not for planning the day.

Same job, other sizes

24 × 12 in footing

Volume for each size. The order columns add 10%, the top of the 5-10% waste allowance, and round bags up.
Sizeft³yd³yd³ to order (+10%)80 lb bags (+10%)60 lb bags (+10%)
10 ft run200.740.813749
15 ft run301.111.225574
20 ft run401.481.637498
24 ft run481.781.9688118
30 ft run602.222.44110147
40 ft run802.963.26147196
50 ft run (this page)1003.74.07184245
60 ft run1204.444.89220294
80 ft run1605.936.52294392
100 ft run2007.418.15367489

At this size

What changes on a 50 ft footing, 24×12 in

Mixing or ordering it

167 × 80 lb bags is 3.7 yd³ - about 84 mixer batches. At this size the bag count is a costing reference rather than a plan: mixing 167 bags on site cannot keep ahead of the setting edge, so the pour ends up full of cold joints. Ordered by the yard it is part of a single load. Have the crew, the access and the discharge points sorted before anything arrives.

How it is worked out

A strip footing is a long rectangular prism under a wall; a spread footing is a pad under a column. Either way the volume is length × width × depth. Enter the total run of the footing as the length, and the trench cross-section as width × depth.

That volume - 100 ft³ - is divided by 27 to give 3.7 cubic yards, and by each bag's yield to give the bag count. An 80 lb bag of premix yields about 0.60 cubic feet, so this job takes 167 of them; bag counts always round up, because you cannot buy part of a bag.

Ordering ready-mix instead? Suppliers sell by the cubic yard (or cubic metre) and usually have a minimum load and a short-load surcharge - worth a call before you choose between bags and a truck.

Formwork

What is being measured